Posts Tagged ‘Texas’

Special Mechanic Lien Rules for Specially Fabricated Materials

Time and time again on this blog, I’ve said that if there is one lien law rule consistent from state to state, it’s that in order to qualify for a mechanics lien claim, the materials or labor you furnish must actually be incorporated into the jobsite’s property (click here to see mentions of “incorporation” on blog).

Sometimes, however, there’s an exception that applies to certain parties who manufacture or supply specially fabricated materials. According to these exceptions, a mechanics lien can be filed for materials created, but not ever incorporated into the property, under certain conditions.  This post discusses what specially fabricated materials are, which states have the exception, and under what circumstances the exception applies.

Specially Fabricated Materials Defined

What exactly is a “specially fabricated material?”  Generally speaking, most states who define this term as “materials not generally suited for or readily adaptable to use” in a structure. As you can see, however, this leaves a lot of room for interpretation.

Specially Fabricated Materials are defined as materials not generally suited for or readily adaptable to use.
As a result, you can think about building materials as being part of a spectrum, with some materials absolutely, positively being specially fabricated for a specific project, and others obviously being your run-of-the-mill standard building material that is not specially fabricated. Then, in the middle, there is some gray area.

Most courts will apply a simple test to decide whether a material is specially fabricated, weighing these two factors:  (1) Were the materials specially ordered and specially fabricated for that specific project?; and (2) Can the produced materials be easily used in another structure?

Survey of State Laws Giving Specially Fabricated Materials Special Treatment

There are a handful of states that specifically discuss specially fabricated materials in their mechanic lien laws. These states typically allow a materialman to file a mechanics lien if they produce the materials, and after production, the materials are not incorporated into the property because the order is cancelled or interfered with by the property owner or general contractor.  Some of these states require a special “specially fabricated materials” notice be sent at the time an order is placed.

Here is a survey of the states with special rules on the books about specially fabricated materials.

Florida

In Florida, there isn’t a statute that excuses specially fabricated materials from the state’s general requirement that materials must be incorporated into the property to qualify for mechanic liens. However, the courts ahve carved out an equity exception to the general rules for specially fabricated materials, providing they are lienable even if they never arrive at the job site, so long as the materials were manufactured to order and the non-incorporation is the fault (either direct, or by direction) of the property owner.

The jurisprudence was established in Lehigh Structural Steel Co. v. Joseph Langner, Inc. by the 1949 Florida Supreme Court, when the court explained as follows:

We are cognizant of the rule that the Mechanics’ Lien Law should be construed so as to afford to mechanics and laborers the greatest protection compatible with justice and equity…And we have previously noted and approved the rule, followed in many jurisdictions, that the real property to be improved is subject to a lien for materials specially fabricated for such improvement under a contract directly with the owner of the realty when such materials are not used or delivered by the act or direction of the owner. There are strong equitable reasons for holding the owner’s property subject to a materialman’s lien in such cases.

Hawaii

Hawaii presents an interesting case, as the statutes do not clearly provide that a party may file a mechanics lien for specially fabricated materials not actually incorporated into the property’s improvement. However, the statutes do mention specially fabricated materials, and therefore, it can be reasonably interpreted to allow a lien in the event these materials are created and never used.

Nevertheless, the statute is not clear on this point, and there doesn’t appear to be any case law interpreting the same.  Here is what the statute says, within H.R.S. 507-41:

“Furnishing of materials” includes supplying of: materials incorporated in the improvement or substantially consumed in construction operations or specially fabricated for incorporation in the improvement; building materials used during construction but not remaining in the improvement, diminished by the salvage value of the materials…

Massachusetts

Massachusetts ALM GL ch. 149, § 29 has a special requirement for those supplying specially fabricated materials, and while the statute doesn’t clearly indicate a mechanics lien could be placed even if the materials were not incorporated into the property, this statute infers the same.

The statute requires that those providing specially fabricated materials must deliver a notice to the property owner within 20 days of when the order for materials is placed. Presumably, if the materials are produced and never incorporated, lien rights would still exist, as the need for the notice doesn’t apply once the specially fabricated materials are built and incorporated. Lawrence Plate and Window Glass Co. v. Varrasso Bros., Inc. At that point, the materialmen is treated like an ordinary material supplier without the notice requirement.

Therefore, the notice requirement is only there to preserve mechanic lien rights in the circumstance that the materials are never installed.

Montana

Montana has a statute dedicated to material suppliers and setting forth the specific circumstances when a materialman has mechanic lien rights, and this statute specifically addresses specially fabricated materials. Mont. Code Anno., § 71-3-524 provides:

(1) A lien for furnishing materials arises only if:
(a) (i) the materials are supplied with the intent that they be used in the course of construction of or incorporated into the improvement in connection with which the lien arises; and
(ii) the intent described in subsection (1)(a)(i) may be shown by a contract of sale, by a delivery order, by delivery to the site by the lien claimant or at the lien claimant’s direction, or by other evidence; and

(b) the materials are:
(ii) specifically fabricated for incorporation into the improvement and not readily resalable in the ordinary course of the fabricator’s business, even though the materials are not actually incorporated into the improvement;

Therefore, the supplier of specially fabricated materials may file a lien if the materials are never incorporated, but only under certain circumstances.  These circumstances in Montana, while statutorily provided, are really similar to the requirements elsewhere that are created by case law.

Nebraska

The rule in Nebraska is very similar to the rule in Montana, as both states specifically address specially fabricated materials in their statutes.  Again, the statutory rule in Nebraska (like Montana) is very similar to the standard created by case law in other states.

Quoting from the Nebraska statute, to file a mechanics lien for non-incorporated specially fabricated materials, the following is required: “Specially fabricated for incorporation in the improvements and not readily resalable in the ordinary course of the fabricator’s business even though not actually incorporated in the improvement.” Neb. Rev. Stat. § 52-134(1)(a)

North Dakota

Similar to the situation in Nebraska and Montana, North Dakota statutes build-in a reference to specifically fabricated materials, suggesting that lien rights exist in the state for material specifically fabricated for a project, but never actually incorporated therein.  The statute in North Dakota specifically provides as follows, in its definition of materials that materials include “custom or specially fabricated materials for incorporation in the improvement.”

Unlike the statutes in Nebraska and Montana, there is no specifying that the specially fabricated materials are worthy of a lien absent incorporation. However, since the statute specifically mentions specially fabricated materials and defines them as materials “for incorporation in the improvement,” it makes one wonder if there is an inference here that they are qualified for lien rights absent physical incorporation.

Tennessee

Tennessee Code Ann. §66-11-101(4)(A)(iii) includes in its definition of “furnish materials,” to “specially fabricate materials for incorporation in the improvement and, if not delivered to the site of the improvement, are not readily resalable by the lienor.”  This definition, like the definitions in some of the others states listed herein, make it evident that there are lien rights if specially fabricated materials are ordered, but not physically incorporated into the building.

Texas

The Texas Property Code provides a specific exception for specially fabricated materials to the general requirement that to file a lien, a supplier’s materials must be used in or delivered to the construction project. Section 53.0231(b) provides – quite clearly – that “A person who specially fabricates material has a lien even if the material is not delivered.”

Such clarity is surprising for a state whose lien laws are among the most complex in the nation.  Ah, but that is not all, of course.  To protect this right to lien for non-incorporated specially fabricated materials, the supplier must send a “Notice of Specially Fabricated Items” to the property owner.

All Other States

In this survey of specially fabricated mechanic lien laws, I’ve focused on those states that have statutes or cases mentioning these types of materials, and even further, allowing liens for the same. Just because a state doesn’t have a statute or a case addressing specially fabricated materials, however, doesn’t mean lien rights for these materials don’t exist.

As you can see in the case referenced under the above Florida discussion, providing lien rights to specially fabricated material suppliers is an equity exception to the state’s general incorporation rule. Every state who has an incorporation rule may, if the circumstances warrant, provide for such an equity exception.

Of course, there are some states who forbid such liens.  There are probably some other states that specifically allow these liens who have been overlooked in this post.  (Readers?  Lawyers?) However, this is a good survey of specific laws addressing this issue, and if you’re in a state not mentioned, you can probably apply the same equity principles to find a mechanics lien right.

Posted in:     The Legal Corner  /  Tags: , , , , , , , , , , , , ,   /   4 Comments

Preserving and Executing Lien Rights Leads to Prompt Payment

Contractors and suppliers have a remarkable collections remedy at their fingertips:   the mechanic’s lien.    But as we’ve (and countless others @constructionlaw @timrhughes @myconstructlaw @matthewdevries) have warned a thousand times…the lien laws vary state-by-state, and they are highly complex.

Preserving those lien rights by promptly and properly filing a preliminary notice, notice to owner, or other type of required construction notice is critical.   Thereafter, timely recording your mechanics lien or public bond claim is also critical.

With all the legal complications and technicalities, some contractors and suppliers may wonder whether the mechanic lien is worth all the trouble?

Yesterday, Walter Duke at the Texas Construction Law Blog may have tendered an answer to this question.   His post, 4 Practical Steps to Help Ensure Prompt Payment, does a great job of focusing the non-payment issue onto four practical efforts.    One of those four important steps?    You guessed it…the mechanics lien.

Here is the praise Walter gives the mechanic lien in his post:

Mechanics liens are one of the easiest ways to ensure payment on a construction project, and yet they are one of the most commonly botched practices among contractors. All other tricks for getting paid on a project rely on the willingness, ability, and legal obligation of another party to pay up.  Liens, on the other hand, place your remedy in the land and its improvements (which, in theory, always have intrinsic value).

I thought this was a nice concise summary of why the mechanic lien is so powerful, and so frequently works.    Rather than regurgitating Walter’s post here, take a look at it on his blog in full to see more of his thoughts on mechanic liens, and the 3 other practical steps to help ensure prompt payment.

Posted in:     Lien Management, The Legal Corner  /  Tags: , , ,   /   1 Comment

Are Texas Lien Deadlines Most Complex in Nation?

Generally speaking, lien laws and deadlines are complicated. The Texas lien statutes, however, may be among the most complex in the nation.

When calculating your deadline to file a lien, there are two features that distinguish the Texas framework from other states.

First, rather than requiring your lien be filed within so many days from the last day of providing labor, the Texas statutes calculate the due date by months, with confusing language like “by the 15th day of the month ___ months after lien claimant completes work.” Second, the notice requirements differ by project, use the same confusing calculation method, and in some circumstances require contractors to re-serve the notice month after month.

One law firm in the Dallas-Ft Worth area has gone so far as to publish a blog post each month with the lien deadlines for work performed during that month.

On our Lien Law Punchlists page, we’ve compiled two charts from lien deadline information published by Texas law firms.   A contractor and supplier can quickly look at this chart to determine when its lien and notice is required.    One is the Lien Deadline Chart and the other is the 2 and 3 Month Notice Chart.    You can also look at our Texas Lien Law Punchlist for a more wordy explanation of these charts.

Posted in:     Mechanic Liens  /  Tags: ,   /   3 Comments

What You Need To Do Immediately After Filing A Construction Lien

So, you filed your construction lien on time.  Whew!   Now what?

If you’re a subscriber to our blog, you know we frequently post about the technical requirements and strict deadlines that lead up to the filing of a construction lien.   We don’t, however, frequently discuss the technical requirements and strict deadlines that follow a lien’s filing.   There are a few, and as usual, these requirements vary state-by-state.

Generally speaking, however, you have to keep two things in mind immediately after filing a construction lien.

First, you may need to send notice of filed lien to the property owner and/or contractors “up the chain.”  In some states (like in Texas) a lien is actually unenforceable unless a copy of the filed lien is delivered to the property owner within 5 days of its filing.   That’s a serious penalty, and a pretty immediate deadline.   Other states have similar penalties (in Oregon, for example, you cannot collect attorneys fees from the other party in foreclosing on lien that was not delivered to the property owner after filing).

Now, here is how Zlien helps.

Any liens ordered from us (in any state) are delivered to the property owner and all other interested parties (those named on the lien) immediately after filing.   Notice of the filing is delivered certified mail, and a record of the mailing is maintained in your online account, available for you to review or download at anytime.   You simply place your order and forget about it – we do all the rest.

Second, liens expired if they are not “foreclosed upon” or “enforced” within a certain period of time.    In some states, liens must be enforced within just 90 days (California), while other states can provide up to 2 years (Texas).   Failure to file a lawsuit enforcing / foreclosing the lien will result in the lien expiring.

How does Zlien help with this?

Well, once you put the “Lien’s Filing Date” into our system, the system will calculate your lien’s expiration date.  If you order the lien from Zlien, we’ll put the date in the system for you.    We don’t actually foreclose or enforce the lien for you (you’ll need an attorney for that), we do give you a heads-up when the deadline is approaching.

Posted in:     Lien Management, Mechanic Liens  /  Tags: , , ,   /   1 Comment

Charts to Make Texas Lien and Notice Deadlines Easy

Texas is unlike any other state when it comes to calculating its lien and notice periods.   Instead of a lien being due after a certain number of days or months, Texas uses somewhat cryptic language to define the lien period:  “on the 15th day of the month four/three months after the last month the claimant performs work.”

WHAT!?!?

Well, to help you out, we’ve created some easy to read charts.   You can take one look at this chart and easily figure out when your lien should be filed.    Check out the Texas Lien Deadline Chart here, or the Texas Two and Three Month Notice Deadline Chart here.   These are housed in the Lien Law Summaries Section of Zlien’s website.

But you don’t even have to go that far – you can see the charts right here on our blog:

Texas Lien Deadline Chart
Work Last Performed In: Residential Liens Due: Non-Residential Liens Due:
January April 15th May 15th
February May 15th June 15th
March June 15th July 15th
April July 15th August 15th
May August 15th September 15th
June September 15th October 15th
July October 15th November 15th
August November 15th December 15th
September December 15th January 15th
October January 15th February 15th
November February 15th March 15th
December March 15th April 15th
Texas Two and Three Month Notice Deadline Chart
Unpaid Work Performed In: 2 Month Notice Due: 3 Month Notice Due:
January March 15th April 15th
February April 15th May 15th
March May 15th June 15th
April June 15th July 15th
May July 15th August 15th
June August 15th September 15th
July September 15th October 15th
August October 15th November 15th
September November 15th December 15th
October December 15th January 15th
November January 15th February 15th
December February 15th March 15th

* Original Contractors do not have notice requirements in Texas

** Two Month Notice must only be delivered by lower tier subcontractors and suppliers (i.e. those who did not contract with the original contractor)

*** If on a residential project, every deadline is one month earlier.

Remember, too, that you can keep track of project deadlines using our free Lien Pilot.

Posted in:     Mechanic Liens, Preliminary Notices  /  Tags: , , , ,   /   Leave a comment

Mechanic’s Lien Solution

  • The most potent tool you have to manage receivables is to preserve, perfect and enforce your mechanics lien and bond claim rights. But, it's so complex? Zlien is a revolutionary enterprise offering to monitor your lien deadlines and automatically file required documents.

Contact Zlien

  • 4819 Prytania Street
    New Orleans, LA 70115
    (866) 720-5436
    email: mail@zlien.com