Don’t Know Who Bonded A State Or Federal Project? Just ask.

Published on January 12, 2010 by Scott Wolfe Jr

In nearly every circumstance, a general contractor on a federal or state project is required to maintain a bond for the work being performed.   These bonds protect the payment rights of subcontractors, sub-subcontractors and suppliers.    In the event any of these parties are not paid on the project, the unpaid party can typically file a claim against the surety who bonds the project as per the Miller Act or a state’s Little Miller Act.  (Read this great article from Construction Business Owner about bonds, generally).

Claims against sureties are beneficial because:  (1) It can reduce the prevalence of personality conflicts between the unpaid party and the general contractor; and (2) It is a guarantee that at the end of a proceeding, money will be there.

However, you can’t make a claim against a surety if you don’t know who the surety is.   And if you’re not on the best of a terms with a general contractor, you may fear that it won’t reveal the surety to you.

So, this begs the question:  how on earth do you discover the identity of a surety?

The answer is quite simple:  Just ask.  That’s right, just ask for it.

Who To Ask?

Under the Miller Act and most Little Miller Act statutes, the public agency in charge of the project is required to (and quite used to) disclose the identity of the surety to anyone who asks for it.

Using Google, you can generally always find the governing authority.   A governing authority will typically manage its contracts through:

(a) public works department;
(b) new construction department;
(c) purchasing department;
(d) capital projects department; or
(e) facilities department

Most of these governing authorities (almost all) will have a website that gives you some information about their public contracts.   Figuring out which department is in charge of the contract is generally a toss up, so you will likely need to navigate around government websites to find the best possible contact.

How to Ask

As I stated above, agencies are required to disclose the surety on the job….actually getting it, just depends on how difficult the agency will make it for you.

If a governing authority has a website, you will generally be able to find out at least a little bit of information about their projects. If the project is relatively new, they might still have bid postings, pictures, articles and reports posted.

Giving the agency a phone call will usually do the trick, but if you run into trouble, just send a certified letter making the request.  You can even have Express Lien send this notice / request for you.   We’ll even figure out who to contact, saving your company valuable time and energy.

Got a Public Contract?: Be Sure to Preserve Your Rights to Payment

Published on December 14, 2009 by Douglas Reiser

Over the past two years, the construction industry has seen a boom in public works. This is due to lower construction costs, influx of federal stimulus funds and lower financing rates for local governments.

The result has meant tons of public work for contractors, who benefit both from Davis-Bacon wages and bonded work, which virtually ensures payment!

Express Lien has taken the time to ensure that its clients know the basics of filing and preserving lien rights on the public job. A recent article describes your rights under the Miller Act, a federal series of laws which govern contracts for construction over the amount of $100,000.00.

But, did you also know that each state has what is called a “Little Miller Act.” These collections of laws mirror the purpose and structure of the Miller Act, namely providing rules for payment, security and claims on the public project.

For instance, did you know that every state or locally managed construction contract issued in Louisiana for a total of no less than $100,000.00, requires a performance and payment bond and demands that you file a sworn statement of your unpaid claim within 45 days of completion? (See La. R.S. 38:2241, et seq.) We’ve have reported on this before.

How about the great state of Washington (our home), which requires that a contractor provide 60 day notice of its right to a lien against a public contract’s retainage? (RCW 60.28, et seq.) Failing to timely file could result in forfeiture to timely payment, and your right to proceed in an action against the contractor’s bond.

Its important that contractors understand that it takes more than simple contractual compliance to ensure payment. Having a qualified lien management company on hand makes it all that much easier to feel secured on the jobsite!

Express Lien’s $395 flat fee services includes tracking down and obtaining copies of the prime contractor’s bond, noticing the surety and prime contractor, and filing with the appropriate state or federal agency, your claim. Remember that our services also include all mailing and delivery confirmation.

Also, remember that in many cases, suppliers, second-tier subcontractors, and equipment lessors, may be required to issue preliminary notices of the materials they sell or lease, or the work that they will perform on a public project. Express Lien’s $35 flat fee notices can save you!

Using Express Lien’s Lien Pilot, you could greatly benefit from tracking deadlines and lien obligations. Please be sure to check out Lien Pilot and keep up with ConstructionLienBlog.com, for more information on how to protect your business.