Louisiana Liens: Guidelines for Materials Suppliers

Louisiana Liens: Guidelines for Materials Suppliers

On September 8, 2009

Lets be brief here: Suppliers are never in the know.

One of the most difficult things to do as a construction attorney is to try and educate your supplier clients about the types of information they need to be collecting when selling materials. Suffice it to say that in the event that you, as a supplier, want to file a lien, you need to be prepared with the requisite information.

What Do You Need to Know?

Here are the necessaries:

(A) The Property Address/Tax Assessor Number - obtaining the legal description is required, but your attorney can generally assist you here. But, you need to make sure you have the right address. Addresses change during remodel and reconditioning of property. So, if you can get the tax assessor parcel number – you are in the best shape.

(B) The Owner Name & Address - Louisiana law provides you with a claim against the property owner (See below) under La. R.S. 9:4802(A)(3). Though your attorney may be able to rescue this information from the property records, its always a good idea to have the information readily available, for purposes of sending pre-lien notices (See below).

(C) The Contractor’s Name & Address - We don’t necessarily mean your contractor client. La. R.S. 9:4802 also provides you with a legal cause of action agains the project’s general contractor. So, please be certain to obtain that contractor’s name in order to send pre-lien notices.

(D) The Dates of DeliveryKeep those bills of lading! Oftentimes lien disputes with suppliers come down to a matter of days in calculating whether or not a lien is timely (see below). It is good practice to keep a log of all material deliveries and keep signed bills of lading to prove delivery.

What Notice is Required?

Suppliers are required to send a Notice of Non-Payment at least 10 days prior to filing any lien. There is a caveat – this notice is only required on residential projects. However, it is good practice to send this notice out on all projects, for purposes of good collection tactics and pre-lien settlement of amounts due.

A notice should include:

(A) the name and address of the seller of movables;

(B) a general description of the materials provided;

(C) a description sufficient to identify the immovable property against which a lien may be claimed, and

(D) a written statement of the seller’s lien rights for the total amount owed, plus interest and recordation fees.

The notice must be sent to the contractor and to the owner via certified mail return receipt.

NOTE: Be advised that in projects where a notice of contract has been filed, there is a cut off date for providing notice. Notice of Non-Payment must be sent out 75 days from the last date of the month in which materials were delivered, and in no event longer than the statutory period for filing the lien.

How and When Do I File My Lien?

A supplier’s lien is filed just like a contractor lien, but there are some additional time obligations.

If a general contractor files a notice of contract and subsequently files a notice of termination then the supplier must file its lien within 30 days from the date of the filing of a notice of termination.

If no notice of contract has been filed, then the supplier has a longer period. In that event, the supplier has until 70 days from the date of substantial completion or from the date of filing a notice of termination.

A lawsuit must be intiated within one year from the date of filing in order to extend the lien and make it enforceable.

How Can I Best Protect Myself?

Under La. R.S. 9:4822(K), a supplier may send the owner and contractor a request for notice, demanding that the owner provide them with the a copy of any notice of termination filed, or otherwise the date of substantial completion, at least three days from filing or declaring substantial completion.

If an owner fails to to provide this information, then they are responsible for your attorneys fees.

It is good practice to put together a notice that goes out to all project owners on projects that you ship materials to.

Being careful and following the rules will ensure that your lien is safe.

Comments (2)
  1. I want to know if their is a Law set that the Contractor does not have to pay is suppliers and or its subcontractors ontell he gets paid from the owner, which is some cases may take months.

    • Hi Rodney. Thanks for visiting and for your comment. To my knowledge, there aren’t any laws out there allowing contractors to withhold payment from subs and/or suppliers until they get paid from the owner. You may be thinking of a “pay when paid” clause, which exists in many construction contracts. Since parties to a contract may contract for whatever set of payment rules they want, the parties to a construction contract may agree in writing that the subs/suppliers will not be paid until the general contractor is paid from the owner. When this agreement is made, a general contractor may be able to withhold payment until it is paid from the owner. That is a product of their contract, and not the law.

      With that said, you must be careful with pay when paid clauses. Each state treats them differently, with some states overturning them and some states upholding them, and then other states interpreting them strictly.

      Take a look at some of these articles I’ve written on my other blog, the Construction Law Monitor, regarding this issue:

      http://www.constructionlawmonitor.com/tags/pay-when-paid/

Leave a Comment

Mechanic’s Lien Solution

  • The most potent tool you have to manage receivables is to preserve, perfect and enforce your mechanics lien and bond claim rights. But, it's so complex? Zlien is a revolutionary enterprise offering to monitor your lien deadlines and automatically file required documents.

Contact Zlien

  • 4819 Prytania Street
    New Orleans, LA 70115
    (866) 720-5436
    email: mail@zlien.com