Virginia – Strongest Liens of them All?

Published on December 29, 2008 by Scott Wolfe Jr

In the past, we’ve posted about the strength and effectiveness of construction liens.    Across the nation, construction or mechanics liens can be used as a powerful collections tool by contractors, suppliers and others working on construction projects.

The state of Virginia, however, has perhaps the most powerful mechanics liens in the nation.

In most circumstances, a mechanics lien will get resolved without the property being foreclosed or the property owner filing bankruptcy.   However, there are occasions (and in this economy, increasingly so) when a project falls apart, and those working on the jobsite find themselves waiting for proceeds to trickle down from foreclosure or bankruptcy proceedings.

In most states, a filed mechanics lien takes priority below the construction loan bank’s mortgage.   Further, the filing of bankruptcy usually defeats any lien rights.

In Virginia, however, the opposite is true.  A properly filed mechanics lien in Virginia will not get defeated in bankruptcy, and it will have priority over the construction loan bank.   Earlier filed mechanics liens have priority over later filed instruments.

We’ve posted in the past on why its important for contractors to lien unpaid construction projects.   This review of the powerful lien laws in Virginia stands as a reminder of how effective a mechanics lien can be, and why its important to make your claim timely & properly.

2 users responded in this post

Subscribe to this post comment rss or trackback url

Chris Hill said in December 29th, 2008 at 8:10 am

Scott,

You sure have been busy! VA mechanic’s liens are quite powerful. However, as astutely pointed out in your other posts here, the requirements are as technical as the tool is strong.

Keep up the good work.

Robert Sumner said in May 1st, 2009 at 8:49 am

It should be noted that VA mechanics lien laws also protect the owner should a contractor abandon a project before completion. 43-16 of the laws provide for the owner to recover all costs of completion when a contractor abandons a project. This section allows the owners cost of completion to have priority over all other liens including the construction lien and may wipe out all other liens should the cost of completion exceed the other lien amounts. Score one for the innocent owner !!